Timeline
The Building 'Our' Productivity research project runs for four years, from early 2008 until the end of 2011. Within that time, a number of milestones have been created against which the success of the project can be measured. These are listed in brief below:
30 June 2008
- Ethics committee approval gained
- Advisory board assembled
- Project manager hired
30 December 2008
- Firm selection completed
- Access to sector one and sector two firms underway
30 June 2009
- Interviews, survey and archival data gathered for sector one
30 December 2009
- Sector one analysis and case study writing underway
- Interviews, survey and archival data gathered for sector two
30 June 2010
- Within sector analysis for sector one complete
- Dissemination of early findings for sector one
30 December 2010
- Within sector analysis for sector two complete
- Dissemination of early findings for sector two
30 June 2011
- Cross sector analysis completed
- Transferability scenarios underway
30 December 2011
- Final dissemination of results