Assessment / exam period, 5 June – 25 June 2023
Disruptive works are being postponed and/or placed on a stop-start timetable over the assessment period. General construction works on the main site and new bus stop site (outside Murphy) will continue with low level impact.
Postponed works
Wastewater Treatment Plant excavation, drilling and piling works at the north end of the site (outside Murphy Annex) have been postponed over the assessment period.
Timber driven piling on the main Living Pā site has also been postponed until after the exam period.
Stop-start piling works
Low impact general construction on the main site and new bus stop will continue. To accommodate exam timetables, any potentially disruptive works during this period will be programmed on a stop-start schedule with a 15-minute buffer each side of exam times.
Whakapā mai—Contact
Please contact Property Services Helpdesk if you have any queries.