The Living Pā contruction site remains very busy with a range of works occuring in different areas.

Kia mataara—Upcoming works

The Living Pā contruction site remains very busy with a range of works occuring in different areas.

1-min read
26 May 2023

Here are the works happening during the end of May through to the first week of June:

  • Timber driven piling works will resume at the south end of main site (Glasgow Tce)
  • Timber superstructure works will be continuing at the main site
  • Waste Water Treatment Plant piling works will continue at the site’s north end (front of Murphy Annex)
  • Excavation works for the new bus shelter will also be underway north of the site (outside Murphy building)

These works will result in the following impact:

  • High impact, noisy drilling works, Monday 29 – Wednesday 31 May.
  • Medium impact vibration and excavation works, Monday 29 May – Friday 9 June.

Ngā whakamahuki—Progress

Glasgow Terrace retaining wall works have been completed.

Ngā mahi e tū mai nei—Future works

An examination period notice will be issued Thursday 1 June. Waste Water Treatment Plant works (front of Murphy Annex) are being postponed until after 26 June, and piling works will continue on the main site outside of exam timetable slots.

We appreciate that this construction may be causing stress and discomfort and wish to thank you for your cooperation and patience.

Whakapā mai—Contact

Please contact Property Services Helpdesk if you have any queries.