Other notable works are a range of single-lane road closures and Waste Water Treatment Plant works in front of Murphy Annexe.
Main site construction work
Monday 21 – Friday 25 August
- Excavation and concrete works to form pile caps for the next grid of columns.
- Excavation works to make space for the installation of a transformer to allow the solar power to be fed back into the main power supply.
Monday 28 August – Friday 1 September
- One-lane closure of Kelburn Parade to install the transformer, 28-29 August. Further information in this post.
Monday 21 August – Friday 1 September
- Concrete finishing work on the southern retaining wall.
Front of Murphy Annex construction work
Monday 21 – Wednesday 30 August
- Low level excavation noise for construction of the waste-water treatment plant (WWTP).
Thursday 31 August
- Moderate noise for installation of Waste Water Treatment Plant tanks by a loader crane immediately in front of Murphy Annexe. Further information about the required one-lane closure in this post.
Arohamai, we apologies for the disturbance caused by construction works.
Ngā whakamahuki—Progress
The top of the building is now wrapped in fabric using the Keder system. An alternative to screeds of building plastic wrapping that goes straight to landfill, this system allows the Living Pā to meet its stringent waste minimisation targets while also enabling further interior building work to continue during blustery and wet weather.