Kia mataara—Upcoming works 18–29 September

The coming fortnight will include works on the roof of the first building, and façade installation.

Kia mataara—Upcoming works 18–29 September

The coming fortnight will include works on the roof of the first building, and façade installation.

2-min read
18 September 2023

Ngā mahi ki te Pā — Site works

During this work period, Waste Water Treatment Plant (WWTP) plumbing works continue, as we work towards completing and enclosing the plant.

Main site construction work


Monday 18–Friday 29 September
  • Roof continues to be installed, causing general construction noise.
  • Façade is beginning to be put in place.
  • Columns continue to be erected at south end.

Front of Murphy Annex construction work

The Waste Water Treatment Plant (WWTP) tanks are now in place, and can be viewed from the Murphy overbridge.

Monday 18 – Friday 29 September
  • Plumbing and backfilling works continues within and around the WWTP, but the drilling is complete.
  • The bus stop has scaffolding around it and is in the process of being built by contractors from Greater Wellington Regional Council.

Ngā whakamahuki—Progress

Last week the Living Pā team hosted a induction for over 100 subcontractors. This group included facade installers, plumbers, scaffolders, lift installers, roofers, landscapers, and more. Read more: Ngā ringa raupa o te pā.

As we see the Living Pā come to fruition, we reflect on the project’s vision:

He pā mataora, he pā kaiao, he pā anamata
A thriving community, a living lab, a bright future.